Thailand Electric Power
As industry revived and began to expand after World War II,
the need for electricity grew. The supply was limited and
unreliable, and some industrial firms and businesses installed
their own generators, mostly fueled by imported oil. In 1958 the
Metropolitan Electricity Authority (MEA) was established to
generate and supply power to Bangkok and adjacent provinces. A
year earlier the government had also set up the Yanhee
Electricity Authority (renamed in 1969 the Electricity Generating
Authority of Thailand--EGAT) to promote development of
hydroelectric power. The first hydroelectric generating facility
was the Phumiphon Dam. Completed in 1964 on the Mae Nam Ping, it
had an installed capacity of 420 megawatts in 1979 and a
potential of 560 megawatts.
Escalating power demand led to construction of a major
oil-fired plant, the North Bangkok Power Station, which went into
operation in 1961. Installed capacity from 1968 totaled 237
megawatts. The capital area became adequately supplied with the
construction of a new oil-fired plant in Bangkok. The South
Bangkok Thermal Power Plant started up in late 1970 with a 200-
megawatt capacity; by 1977 this was increased to 1,300 megawatts.
The country's second major hydroelectric plant, at the Sirikit
Dam (potential generating capacity of 500 megawatts) on the Mae
Nam Nan, a major tributary of the Chao Phraya, started generation
with an installed capacity of 375 megawatts in 1974. A third
large hydroelectric facility, part of a multipurpose irrigation,
flood control, and power project at Ban Pho on the Mae Nam Mae
Klong northwest of Kanchanaburi, was completed in the 1980s with
an initial capacity of 360 megawatts and an estimated potential
of 720 megawatts.
Generating capacity to other parts of Thailand was on a much
smaller and regionally unequal scale. Increased oil prices in the
1970s stimulated a new interest in lignite, and a lignite-fueled
plant installed at Mae Mo, the site of a major lignite deposit,
was producing 825 megawatts by 1987. Lignite reserves were
estimated to be 865 million tons in 1985.
In the South a lignite-fired plant at Krabi with an installed
capacity of sixty megawatts commenced generation in 1964. A major
purpose of this plant was to furnish power for tin mines in the
area and the tin smelter on Phuket Island, in addition to meeting
local needs. In 1968 additional generating capacity was installed
on Phuket through a ten- megawatt-capacity diesel plant, and
between 1971 and 1977 three gas turbine units totaling forty-five
megawatts were installed on Hat Yai. In the late 1970s, three
additional gas turbine units having a combined capacity of fortyfive megawatts were also located at Surat Thani.
Development of power facilities in the Northeast received
little attention until the mid-1960s, at which time the region
had an estimated generating capacity provided by small diesel
units of perhaps one megawatt. By the early 1970s, however, four
hydroelectric plants had been installed at dams in different
parts of the region, with an installed capacity of ninety-five
megawatts. New gas turbines furnished an additional thirty
megawatts, and diesel units produced an additional four
megawatts.
In 1987 the power sector was composed of three governmentowned enterprises: EGAT, under the Office of the Prime Minister,
was the national power production agency; MEA, under the Ministry
of Interior had responsibility for power distribution in Bangkok
and the provinces immediately around the city; and the Provincial
Electricity Authority (PEA), also under the Ministry of Interior,
distributed power throughout the rest of the country. There were
also a number of privately held distribution franchises that
bought power from PEA or EGAT. Some privately owned industries
also generated their own power. Installed generating capacity in
1986 was 7,570 megawatts, of which 70 percent was thermal and 30
percent hydropower. In 1985 industry used nearly 50 percent of
the 20 million megawatt-hours of energy consumed. Residential
consumption was 25 percent, commercial establishments used 25
percent, and street lighting and miscellaneous uses accounted for
less than 1 percent. By the end of 1986, nearly 43,000 villages
of the more than 48,000 throughout the country had been supplied
with power. It was projected that 95 percent of all villages
would have electricity by 1991 and essentially all villages by
1999.
Data as of September 1987
|